KSEB to invest Rs.760 crore in 2006-07Illustrative image – not actual.

The Kerala State Electricity Board plans capital investments to the to the tune of Rs.760 crore in 2006-07. The company will invest the Rs.250 crore on generation, Rs.218.50 crore on transmission, Rs.290 crore on distribution and Rs.1.50 crore on other works.

New Hydel projects:
As per the estimates of aggregate revenue requirement submitted to the State Electricity Regulatory Commission, the board proposes to start work on 16 new hydel projects in 2006-07 with a total installed capacity of 423 MW. The aggregate capital outlay for the projects is Rs.82 crore.

The projects include:

Project Capacity (MW)
Athirapilly 163
Pallivasal extension 60
Thottiar 70
Mankulam 40
Barapole 21
Kakkadampoil 21

Apart from these, three ongoing projects of a total installed capacity of 128.75 MW is scheduled for completion by end 2006.The projects are:

Project Capacity (MW)
Kuttiadi additional extension 100
Neriamangalam extension 25
Kuttiadi tailrace 3.75

The board will also invest Rs.40 crore on the ongoing renovation and modernisation of Sabarigiri and Neriamangalam hydel projects in 2006-07.

Transmission sector:
The company plans to invest:

Project Capacity (kV) Cost (Rs. in crores)
Four substations & transmission lines 220 71.65
Ten transmission lines 110 52.73
Three transmission lines 66 18.86

Distribution front:
On the distribution front, the board is targeting five lakh new connections. Besides, the programme for the year includes construction of 6,000 kilometres of 11 KV lines; 17,000 km of low-tension lines; installation of 8,500 distribution transformers and replacement of four lakh faulty meters.

The board has also made a provision of Rs.175 crore under the Accelerated Power Development and Reforms Programme for the year 2006-07.

 