KSB Pumps completes equipment test for ST-CMS power projectIllustrative image – not actual.

KSB Pumps Ltd has completed the testing the third boiler feed pump for ST-CMS Electric Company's 250 MW lignite power project coming up at Neyveli in Cuddalore district of Tamil Nadu. The tests were conducted in full-load conditions on the specially built new test bed at KSB Pumps’ power project division at Chinchwad.

 

The boiler feed pumps form part of the Rs.7.2 crore order, awarded to KSB Pumps by Alstom Power, the EPC contractor for the project, for delivering high pressure ring section boiler feed pumps.

 

The 250 MW power project is expected to be completed by November 2002 at an estimated cost of $300 million.