Illustrative image – not actual.Coastal Andhra Power, a subsidiary of Reliance Power, will commission its 4,000 MW Krishnapatnam ultra mega power project (UMPP) eight months ahead of schedule as the Central Electricity Regulatory Commission (CERC) has okayed changes in configuration of the UMPP.
The company, while bidding for the project, had proposed to set up five units of 800 MW each. However, later on it asked CERC to allow the company to change this to six units of 660 MW each and that the company will advance commissioning of the first unit by three months and of the project by eight months.
CERC has done so and the UMPP will now be commissioned in July 2015 while Unit I will be completed by June 2013.