Krishnapatnam power project Phase I underwayIllustrative image – not actual.

Work on Phase I of Meenakshi Group's 540 MW coal based power project at Krishnapatnam, Thammenapatnam Village, Chillukar in Nellore district of Andhra Pradesh is underway.

Company officials informed ProjectsToday that the project was being set up in two phases, each with a capacity of 2x135 MW. The power plant spread over 225 ha entails an investment of Rs 3,000 crore. Meenakshi was in the process of achieving financial closure for the project which will have a debt equity ratio of 75:25. Development Consultant has been appointed as consultants for the project.

Around 0.86 million tpa of imported coal will be required for Phase I, which is slated for commissioning in February 2012. Work on Phase II is likely to begin by October 2009 with completion scheduled for August 2010.

Meanwhile, Meenakshi Power, a subsidiary of Meenakshi Group has commissioned its 25 MW Middle Kolab Hydel power project located in Koraput district of Orissa.

Related Links:
Project profile

prjexcl
← All latest storiesBack to top →