Illustrative image – not actual.The
Gujarat State government has reallocated 2.25 mmscmd (million metric standard
metres per day) of gas from the Tapti fields to the 615 MW power project being
jointly promoted by Kribhco Energy Ltd (KEL) and Gujarat Power Corporation Ltd
(GPCL).
This
allocation would be enough for the plant to operate at a plant load factor
(PLF) of 68.5 per cent. To step up the PLF, the plant would have to seek
alternate fuel arrangements.
Meanwhile,
global tenders for the selection of EPC contractors for the project were
floated on 14 December 2000.
KEL
holds an equity stake of 89 per cent in the Rs.2,200 crore project while GPCL
holds the remainder.The project is coming up at Rajula that is 12 km from
Pipavav in the Amreli district of Gujarat.