Illustrative image – not actual.Kribhco (Krishak
Bharati Co-operative Ltd) has paid Rs.20 crore to Gujarat State Petroleum
Corporation as part-payment of its 25 per cent stake in Gujarat Energy
Generation Ltd’s (GSEG) 156.1 MW natural gas combined cycle plant being set up
at Hazira in Gujarat.
The remaining
Rs.23.75 crore is likely to paid by March 2001. The equity component of the
Rs.576 crore project is Rs.173 crore, and Kribhco’s stake of 25 per cent works
out to Rs.43.25 crore.
The project
reportedly achieved financial closure in the end of November 2000.