Illustrative image – not actual.
Kalpataru Power Transmission (KPTL) and Techno Electric & Engineering Company (TEECL), a joint venture (JV) partner in KMTL, has completed transfer of 49 percent stake (23 percent by KPTL and 26 percent by TEECL) in Kohima-Mariani Transmission (KMTL) to Apraava Energy.
The remaining stake in KMTL will be transferred by KPTL in accordance with the terms of the transmission service agreement (TSA).
KMTL is a JV between KPTL and Techno Electric & Engineering Company (TEECL) with KPTL holding 74 percent and TEECL holding 26 percent equity. KPTL and TEECL had entered into a binding agreement in July 2019 with Apraava Energy to sell their respective stake in KMTL.
KMTL was set-up to implement a transmission system under the North Eastern Region Strengthening Scheme (NERSS-VI) on BOOM basis. The project was won under a competitive bidding process conducted by PFC Consulting (PFCCL).
The project involved design, financing, construction, commissioning, operation and maintenance of 254 ckms of 400 kV transmission line, 400/220 kV GIS substation of 16 bay, seven x 167 MVA capacity with remote security and remote communication features.
The transmission line passes through three states i.e. Manipur, Nagaland and Assam. The project achieved full commissioning in H2/2020-21.
Ernst & Young (EY) and Khaitan & Co are advisors to KPTL for this transaction.