KPI Green's progress on GUVNL's IPP solar project, targets early completionIllustrative image – not actual.

KPI Green Energy which secured a 200 MW central transmission utility (CTU)-connected independent power producer (IPP) solar project from Gujarat Urja Vikas Nigam (GUVNL) in August, 2023, is targeting an early completion. The company is determined to exceed the SCOD target through a combination of efficiency and quality standards.

The power purchase agreement (PPA) was finalised on 01 March, 2024, with a scheduled commercial operation date (SCOD) set between 31 May, 2025, and 30 November, 2025, that is, 15 to 21 months from signing. 

Upon completion of the Khavda project, KPI’s operational IPP portfolio will expand significantly, growing from 171 MWp to 411 MWp, marking a substantial milestone in renewable energy contributions. The project features an IoT-powered robotic cleaning system which ensures approx. 98 percent cleaning efficiency.

This system, capable of dry cleaning one MW in under three hours, is both sustainable and resource-efficient, drastically reducing water usage. With 550 dedicated robots, the entire 240 MWp plant can be cleaned in just three hours, promising substantial cost and resource savings over its 25-year lifecycle. Further enhancing operations, KPI’s Network Operations Center (NOC) facilitates real-time monitoring and centralized control. This advanced system provides instant alerts, supports data-driven decision-making, and ensures consistent energy production.

 

← All latest storiesBack to top →