Illustrative image – not actual.KPI Global Infrastructure is setting up 50 MW solar photovoltaic power unit (Phase-I) at Sudi village in Bharuch district of Gujarat.
In August 2015, the company received all necessary clearances. The cost of the project is Rs 400 crore.
As per the latest development available with Projects Today, out of the 50 MW, work on 20 MW has been completed in which 2.2 MW was commissioned. Work on 30 MW was still underway with completion scheduled for December 2019.