KPCL to undertake Bellary thermal power project on its ownIllustrative image – not actual.

The Karnataka Power Corporation (KPCL) has decided to go ahead with the 500 MW Bellary Thermal Power Station (BTPS) on its own, since the joint venture partner, Jindal group, has not yet committed its equity stake in the project. The project is expected to be completed by December 2005.

 

As per the original arrangement, in turn of Jindal group’s 25 per cent equity acquisition, KPCL would had to pick an equivalent stake in the expansion project of Jindal Thermal Power Project. But KPCL has not committed any equity stake in this project.

 

The Bellary thermal project cost, estimated at Rs.2,230 crore, would be funded through 80: 20 debt equity ratio. Based on the debt equity ratio, KPCL would have to infuse at least Rs.450 crore by way of equity. In the event of the Jindal group finalising its equity stake in the project, the equity would come down proportionately.

 

It may be added that the work on the Bellary project has already begun and negotiations are under way with BHEL for supply of equipment, which includes boiler as well as turbines. However, the power purchase agreement between the bulk buyer/buyers has not yet been finalised, but is expected to be taken up during the course of the next year.

 

Since the PPA has not yet been finalised, KPCL proposes to raise the project debt funding through short-term borrowings from commercial banks.

 

 