Illustrative image – not actual.Mangalore Power Company (MPC) is
likely to invite Karnataka Power Corporation (KPCL), a State Government-owned power
generating utility, as partner in its 1,013 MW coal-based power project at
Mangalore in Karnataka.
This would be done with a view to reassuring financial institutions (FIs) about the State’s commitment to the project. FIs have been insisting on escrow cover for the project from the State Government.
% This follows difficulty in obtaining central counter-guarantee for the project.
Till now, MPC has made little headway in securing the counter-guarantee from
Government of India which has linked it to escrow support — activating the
escrow account at least 90 days before commercialisation of the plant — from
Karnataka.
The guarantee is essential for achieving financial closure. The state, which
again wrote to GoI this week seeking counter-guarantee for the Mangalore power
project without any escrow cover, has argued that it cannot be placed in the
same basket as other defaulting states.
Sources said chief minister S M Krishna strongly pleaded the state’s case with
the Centre last week on the same grounds.
Karnataka’s contention is that it is one of the few states to press ahead with
energy reforms. Karnataka Power Transmission Corporation has never defaulted on
payment to central power generating stations or any of its equipment vendors.
The recent power tariff hike and series of efficiency measures may push monthly
earnings to about Rs 400 crore. KPTCL’s receivables from different customers is
down from Rs 1,500 crore to Rs 1,000 crore, which is just about three months’
billing.
The delinking of the distribution arm into private hands may further enhance
revenues improving the fiscal health of KPTCL. Besides, the state has taken a
policy decision not to offer escrow support to any IPP with the exception of
Tannirbavi power project which secured this through a legal battle.
Mangalore power project has been envisaged on a 73:27 debt-equity basis. The
project — it takes off this year — is expected to begin feeding into the grid
towards 2004-05 at a levelised tariff of under Rs 3 per unit at current coal
prices.
The project is to be implemented on a project recourse basis which implies that
project creditors including equipment financiers will have to rely only on
project cash-flows.