The Government of Karnataka has reportedly
permitted State-owned utility, Karnataka Power Corporation Ltd (KPCL) to sell
power directly to consumers from the seventh unit of the 210 MW Raichur Thermal
Power Station (RTPS).
The State Government has, however,
not allowed any of the independent power producers (IPPs) in the State, with
whom PPAs have been signed, to undertake third party sales. Almost all IPPs had
sought permission for third party sales from the State Government, in order to
make their projects fully bankable and allow them to operate even in the face
of lower demand from bulk power purchasers.
IPPs had maintained that third party
sales would ensure that the project's cash flows are not dependent on a single
buyer. Third party sales would allow the project to be available both for
meeting contracted demand as well as some spot demand. Such sales would allow
for certain minimum cash flows at least to meet some of the debt service
payments, without the need to invoke any of the security mechanisms. Lenders to
power projects have also been insisting on third party sales for this reason.
The State Government, however, turned
down the IPPs’ demand on the grounds that such sales would adversely impact
revenue flows to Karnataka Power Transmission Corporation Ltd (KPTCL). However,
the concession was extended to Unit 7 of the RTPS, which is the first state
public sector project being modelled on the lines of an IPP.
In extending this concession, however,
KPTCL has imposed certain conditions on KPCL. These are as follows;
- The first right of refusal would be vested with KPTCL.
- Third party sales will not be permitted at tariffs lower than what
is being charged by KPTCL to the existing high tension consumers. This is
to ensure that KPTCL's customer base is protected.
- KPTCL has sought sharing of 50 per cent of the amount realised from
third party sales. This is to be netted against the wheeling charges and
the tariffs payable to KPCL for purchase of power.
Third party sales have been permitted
with a view to improving the project's return on equity. Currently the return
on equity permitted is 16 per cent at a plant load factor (PLF) of 68.5 per
cent. However, if the project is allowed to operate at a higher PLF, then the
rate of return improves. The incentive payment for Unit 7 has been fixed at 40
paise per unit for a PLF in excess 68.493 per cent.