Illustrative image – not actual.Bowing to the demands of the environment activists the Karnataka Power Corporation has altered the technical parameters for the Bedthi Hydel project. In its revised form the hydel project will be taken as a run-of-the-river project and not as a 400 mw storage reservoir-based project across the Tathihalla River in Uttar Kannada in Karnataka which had received clearance in 1977.
Environmentalists and local action
groups had opposed the project on the grounds that the project fell within an
ecologically fragile zone coming in the Western Ghat Biosphere. Besides this,
the project envisaged the construction of a dam, which was likely to submerge a
large area of land thereby adversely affecting the life of people in the
adjoining villages.
With the changes in the technical
parameters, the power project envisages augmentation of the waters through a
small barrage at the already existing dam at Tathihalla and building of a run
of the river turbine. Besides, the power availability from the project was
expected to be lower at not more than 600 million units as compared to the
estimated 900 million units, when the project was envisaged as a storage
project. However, the augmentation of the waters was expected to result in an
increase in power from Nagjari, Kodasalli and Kadra power houses, which was
expected to neutralize the negative impact of the changes made to the
parameters.