Illustrative image – not actual.Konkan Railway Corporation Ltd (KRCL) would
be embarking on a Rs.5,600 crore railway project in Jammu & Kashmir, on 10
June 2003. The project is a challenging one for KRCL given the difficult
geographical conditions and the inclement weather conditions in the state.
The J & K rail project entails the
laying of a 280 km railway line between Udhampur and Baramulla. Of this KRCL
would be laying 92.5 km between Katra and Laole, while the rest would be done
by the Northern Railway and another private firm.
KRCL’s component involves construction
of approach roads to various sites besides 50 bridges (covering a total distance
of 12.8 km), eight stations and two cable-stayed bridges – one on the Chenab
river (800 metres) and the other at Anjikhed (410 metres). KRCL would also be
providing other related infrastructure for the functioning of this stretch
including station premises, electrification, etc.
The work would commence in mid-June with
the excavation of the 2.6 km Gunni tunnel. The cost of this tunnel, with a width
5.2 metres and height of 6.9 metres, will be Rs.45.7 crore. The entire project involves 47 tunnels covering
57.7 km.
The project is scheduled for
commissioning before 15 August 2007.