Konkan Railway completes electrification of 741 km routeIllustrative image – not actual.
The Konkan Railway Corporation has completed electrification on its entire 741 km route between Roha in Maharashtra and Thokur in Karnataka. 
 
The Commissioner of Railway Safety's (CRS) inspection of the last section between Ratnagiri and Thivim was carried out on 24 March 2022 and authorisation was obtained on 28 March 2022. 
 
The CRS inspection of the entire Konkan Railway route was successfully held in six phases starting from March 2020.  
 
The foundation stone of the electrification project was laid in November 2015. The total cost stood at Rs 1,287 crore. 
 
Train operations with electrical traction will be implemented on the route in a phased manner.