Illustrative image – not actual.Kolkata's East-West Metro corridor project, worth Rs 4,874 crore, is expected to face fresh hurdles after already confronting problems in land acquisition.
ITD Cementation, the contractor that had received a contract for tunnelling work on the five km stretch of the project, estimated to cost around Rs 910 crore, is likely to seek compensation of around Rs 200 crore, as it could not commence work on the three km stretch for the last 18 months. ITD Cementation has already completed two km tunnelling work in July 2013.
The Kolkata East-West Metro corridor project has been undertaken by Kolkata Metro Rail Corporation (KMRC). The contractor is demanding compensation from KMRC as it has been incurring losses for deployment of equipment and manpower for the project which has been delayed by almost three years.
Another hurdle for the metro project was realignment of the original route, for which the West Bengal government proposed an alternative route to relocate 250 shops and a few apartments on a half km stretch in Central Kolkata.
The metro rail will start from Howrah railway station to Salt Lake, a length of 14.67 km with a total 12 stations. The project will be developed in phases. Phase-I starts from IT township of Salt Lake to Sealdah.