Kolkata township far from completionIllustrative image – not actual.

Kolkata West International City's (KWIC) proposed township at Salap in West Bengal is facing inordinate delays.

The project has not even completed its Phase I since its inception in 2005. So far, KWIC has handed over only 169 of the 912 villas slated to be built on 82 acre in Phase I. Another 100 houses are awaiting completion certificate in the absence of an access road. As per the original plan, Phase I was to be completed by December 2008. However, latest company communications to buyers mentions Phase I completion in 2012.

The Rs 6,000-crore satellite township was to come up on 390 acre at Salap in five phases. The township was to comprise 11,000 villas and row houses, condominiums, hospitals, schools and commercial complexes and others. In 2006, the Kolkata Metropolitan Development Authority had agreed to offer the land on long-term lease to the Salim Group of Indonesia and its local partner, Singapore based Universal Success at Rs 95 crore.