Kolkata Metro extension projects expected to be completed by Dec 2019Illustrative image – not actual.
Work on six Kolkata Metro extension projects is expected to be completed by December 2019.

Of the six projects involving an additional 99.3 km at a sanctioned cost of Rs 21,811.52 crore, the Kavi Subhas-Hemanta Mukherjee Phase-I, stretching over 5.3 km, and the 10 km long Hemanta Mukherjee-Salt Lake sector V of the Kavi Subhas-Airport corridor have been targeted for completion by June 2019 and December 2019, respectively.

The Noapara-Baranagar-Dakshinesdwar long 3.93 km stretch is supposed to be completed in June 2019, while the nine km long Joka-Majherhat is scheduled for completion by December 2019.

The 5.3 km long Noapara-Jessore road of the Noapara-Airport-Barasat project has been targeted for completion by 2019. The six km stretch of sector V-Phulbagan will be completed in June 2018.

The new Chinese and ICF metro rakes for Kolkata metro will also be soon in place.