Rail Vikas Nigam (RVNL) has completed the basic work for the Orange line of Kolkata Metro underground tunnels along the median of VIP Road, covering 72 mtrs. With the construction ready to enter a crucial phase, that is, curving toward the airport.
RVNL has sought a rejig of the existing traffic block, having built another new stretch of road space to ease movement of Kolkata-bound traffic. A five-day traffic trial is likely next week, before Bidhannagar traffic personnel will hand over the site for the next phase of the metro work.
Implementing the New Garia-Airport (Orange) line, RVNL split the construction of the last leg into three phases so that there is no traffic disruption on the crucial lifeline (VIP Road) that connects the city with the airport. In its last leg, the mostly elevated 29 mtrs. Metro corridor goes underground; wherein contractors Afcons have been tasked to build a 300 mtrs. ramp and 500 mtrs. of twin tunnels in the cut-and-cover method.