Illustrative image – not actual.The Central Electricity Authority (CEA) has accorded techno-economic clearance (TEC) to National Thermal Power Corporation’s (NTPC) 800 MW Kol Dam hydro electric power project in Bilaspur district of Himachal Pradesh.
The estimated completed cost of the project
is Rs.5,300 crore. The project envisages utilization of power potential of the
Sutlej river for electricity generation. This is NTPC’s first hydro electric
project. The project would involve construction of a 163 metre high rock fill
dam across the river Sutlej 6 kms upstream from the existing Dehar power station
and installation of 4 units of 200 MW each.
The project was earlier accorded TEC by CEA in August 1988 for execution in the state sector, but could not be taken up for execution due to various reasons. The project is now proposed to be implemented in the central sector by NTPC. The power generated would be evacuated to the power deficient northern region through 400 kV integrated transmission system lines constructed for Nathpa Jhakri and Kol Dam projects. The project is scheduled to be completed in a period of six and a half years.
The height of Kol Dam has been limited to 163 metres to avoid submergence of Suni township having a population of over 10,000 people. An amount of Rs.97 crore has been provided for environment and ecology measures, while Rs.75 crore have been earmarked for resettlement and rehabilitation. The project has received clearance from the Union Ministry of Environment & Forests.