Illustrative image – not actual.Kochi Port Trust is seeking budgetary support from the Centre to fund the shortfall in implementing its modernisation projects. A cumulative investment of over Rs.1,029 crore is to be entailed in the development of internal and external infrastructure.
It may be recalled that the Finance Minster, Mr Jaswant Singh had in his Budget speech had stated that the Government would provide the viability gap funding to bridge any shortfall to facilitate modernisation of JNPT and Kochi Port.
Kochi Port has put the viability gap at Rs.560 crore as a one-time up front payment or Rs.880 crore in case of funding made in stages.
The development of internal infrastructure includes site development, internal roads and street lighting at a cost of Rs.47 crore while the external infrastructure includes dredging, rail and road connectivity and breakwater costing Rs.982 crore.