Illustrative image – not actual.
Kochi Metro Rail (KMRL), the special purpose vehicle for executing the Kochi Metro Rail project, is soon likely to complete the financial closure for Phase-I, costing Rs 5,181 crore. The project has so far received a domestic loan from Canara Bank to the tune of Rs 1,170 crore and foreign funding of Rs 1,500 crore (€180 million) from the French funding agency, AFD.
A major part of land acquisition has already been completed. Of the 40 ha required, more than 33 ha has already been procured. However, the company is still struggling to obtain the remaining 6.8 ha along the Vyttila-Pettah stretch.
Thus, it is being proposed that Phase-I might end at Vyttila due to delay in land acquisition, so that the project can be commissioned as per the deadline.
Related Link:
Project Profile