Illustrative image – not actual.
The Kochi Metro Rail (KMRL) has conducted trial run on its Phase 1-A extension from Petta to SN Junction on 14 February 2022.
The Metro train ‘Vaigai’ began the trial run on the new track from the second platform of Petta station and the first stretch of the trial run culminated at SN Junction station.
The 25 km stretch from Aluva to Pettah, part of the Phase 1-A, was constructed by Delhi Metro Rail Corporation (DMRC). The construction of the Phase 1-A extension began in October 2019.
The total distance of the line, which is expected to be commissioned within a few months, is 1.8 km. The Metro will have one stop at Vadakkekkotta between Petta and SN Junction. The works of the Vadakkekkotta and SN Junction stations are in its final stage.
The total cost of the Phase 1-A extension from Petta to SN Junction is Rs 453 crore. Of the total amount, Rs 99 crore was spent for land acquisition for construction of two Metro stations.
Moreover, work of Phase 1-B extension from SN Junction to Tripunithura is also under progress.