Illustrative image – not actual.Petronet CCK Ltd's 292 km long Kochi - Karur pipeline is likely to be ready by December 2001. This was stated by the company's vice president, Mr B.R. Pillai.
The pipeline, which covers three districts in Tamil
Nadu and Kerala, was originally scheduled for commissioning in December 2000.
However, though the 143 km stretch in Tamil Nadu was ready by October 2000, work
on the Kerala side commenced only during October 2000. The delay was a result
of rains, litigations, disputes and delays in clearances from various government
departments such as irrigation, forests and national highways.
Fortunately, now only 7 km of the pipeline has to be
laid. Restoration work has also started and is expected to be completed on
time. Land compensation to the extent of 90 per cent has been paid, while the remaining
would be paid soon.
In Kerala, the pipeline passes through 10-17 metres below
three river beds using the horizontal directional drilling without disturbing
the course of the river. This work was done by a Malaysian company, Mersing.
On commissioning, the pipeline will have a throughput
of 3.3 million tonnes per annum (mtpa). This would be increased to 4 mtpa in
the second phase. The pipeline would be used to handle MS, HSD and SKO. On a
hourly basis, 521 kilolitres would be pumped, which means that 12,500 kilolitres
would be pumped per day. The pipeline would have a pumping stream of 8,000
hours per annum.