Kochi - Karur pipeline likely to be ready by DecemberIllustrative image – not actual.

Petronet CCK Ltd's 292 km long Kochi - Karur pipeline is likely to be ready by December 2001. This was stated by the company's vice president, Mr B.R. Pillai.

 

The pipeline, which covers three districts in Tamil Nadu and Kerala, was originally scheduled for commissioning in December 2000. However, though the 143 km stretch in Tamil Nadu was ready by October 2000, work on the Kerala side commenced only during October 2000. The delay was a result of rains, litigations, disputes and delays in clearances from various government departments such as irrigation, forests and national highways.

 

Fortunately, now only 7 km of the pipeline has to be laid. Restoration work has also started and is expected to be completed on time. Land compensation to the extent of 90 per cent has been paid, while the remaining would be paid soon.

 

In Kerala, the pipeline passes through 10-17 metres below three river beds using the horizontal directional drilling without disturbing the course of the river. This work was done by a Malaysian company, Mersing.

 

On commissioning, the pipeline will have a throughput of 3.3 million tonnes per annum (mtpa). This would be increased to 4 mtpa in the second phase. The pipeline would be used to handle MS, HSD and SKO. On a hourly basis, 521 kilolitres would be pumped, which means that 12,500 kilolitres would be pumped per day. The pipeline would have a pumping stream of 8,000 hours per annum.