KNR Tirumala Infra gets provisional completion certificate for Chittoor-Mallavaram sectionIllustrative image – not actual.
KNR Tirumala Infra has received provisional certificate of completion for Chittoor-Mallavaram section in Andhra Pradesh effective from 10 May 2021.  
 
The scope of work includes six-laning of NH-140 from Chittoor (design 0.000 km/existing 158.000 km of NH-4) to Mallavaram (design 61.128 km/existing 41.800 km of NH-140) (design length 61.128 km) in the state of Andhra Pradesh under Bharatamala Pariyojana on hybrid annuity mode (HAM)
 
The certificate was received by KNR Tirumala Infra, a wholly-owned subsidiary of KRK Constructions and the project was completed 142 days ahead of the revised scheduled completion date with an entitlement of bonus.
 
The bid project cost is Rs 1,730.07 crore. The appointed date for the project was 4 January 2019 with a construction period of 910 days.
 
The quantum of bonus based on original scheduled completion date is Rs 8.99 crore and if revised schedule completion date is taken into account, it will be Rs 24.57 crore.