KNR Constructions completes road project in KarnatakaIllustrative image – not actual.

KNR Constructions has completed work on a road project in Karnataka in 582 days against the scheduled duration of 910 days, 11 months ahead of time.

The company has completed work on 97.221 km of road project on National Highway (NH) 13 in the Bijapur-Hungund section in Karnataka under NHDP Phase III. The project included construction of an 810 mtrs dual carriageway bridge over river Krishna on National Highway 13 (recently changed to NH-50) near Almatti in a record time of 11 months and 16 days.
 