Illustrative image – not actual.KNR Construction has achieved financial closure for a road project in Kerala. KNR's subsidiary -- KNR Walayar Tollways -- has signed the financing documents with Central Bank of India, Bank of India, Corporation Bank, Canara Bank and Vijaya Bank.
The venture, estimated to cost Rs 900.51 crore, would be financed by means of equity of Rs 135.91 crore; grant of Rs 264.60 crore; and debt of Rs 500 crore.
The project is for four-laning of 53.89 km Walayar- Vadakkancherry section of NH- 47 from km 182.25 to km 240 under NHDP Phase II, through PPP route on DBFOT basis. The concession period for the project is 20 years including construction period of 910 days.