Illustrative image – not actual.The Ministry of Road Transport & Highways (MoRTH) has asked the Haryana government to restart work on the much delayed Kundli-Manesar-Palwal (KMP) Expressway within two months, as work on the project was progressing at a very slow pace.
The 135 km long expressway project, undertaken by DS Construction, has missed several deadlines since its inception in 2006.
The Ministry has asked the Haryana government to resume work on the project within two months, failing which the ministry will hand over the balance work to National Highways Authority of India (NHAI).
The project was earlier slated for completion by July 2009, but due to the slow pace of work, only about 70 per cent has been completed till date.
An amount of Rs 1,200 crore has been spent so far on the project and a balance of Rs 1,500 crore is yet to be spent.
MoRTH has asked the Haryana government to settle things with the concessionaire and has offered to return to the state government the expenses incurred on the project, stating that the balance will be spent by the Ministry on completion of the project.
The original cost of the project was Rs 1,915 crore, but due to changes in the scope of work, the cost of the project has now escalated.