Illustrative image – not actual.The NHAI Board has failed to arrive at a compromise to rework as per the conditions of GMR for Kishangarh-Udaipur-Ahmedabad project.
Kishangarh-Udaipur-Ahmedabad project is the 555-km project, the country’s longest highway stretch, from which GMR had wanted to exit citing delays in environment clearances. However, it subsequently submitted a proposal to NHAI citing that it was willing to take on the project subject to certain conditions. For the first five years of operation, GMR did not want to pay premium. It also wanted compensation for project cost increase for delays in environmental clearance and machines lying idle. According to the project bid, GMR was supposed to pay a premium to NHAI for 26 years, with the premium being Rs 636 crore in first year. In subsequent years, the payout will have increased by five per cent.