The Expert Appraisal Committee (EAC) of the Union Environment Ministry has given approval to the Rs 4,640.88 crore Kiru hydroelectric power project to be developed on Chenab river in Kishtwar district of Jammu and Kashmir. Based on its recommendations, the ministry will soon take a call on giving the final green nod.
The 623 MW Kiru project will be developed by Chenab Valley Power Projects, a joint venture among NHPC, J&K State Power Development Corporation and Power Trading Corporation of India.
The project envisages construction of a 123 metre (from river bed level) high concrete gravity dam across river Chenab with four intakes, four pressure shafts, and underground powerhouse of four units of 156 MW each. The construction period of the project is 54 months.
As per the recommendations of the EAC, out of the total project cost, the Environment Management Plan (EMP) budget is Rs 147.32 crore i.e. about 3.2 per cent. However, the overall EMP budget should be raised to 3.5 per cent of the project cost.