Khurda-Balangir railway project prioritizedIllustrative image – not actual.
Odisha state government will sign an MoU with the Railways ministry on 20 July 2015 for the completion of the 289 km Khurda Road-Balangir railway project.

 

The project sanctioned in 1994-95 at a cost of Rs.1,000 crore saw its outlay doubling to Rs.2,000 crore because of inordinate delay in execution. Non availability of land is the major reason for the slow progress in the implementation of the project.

 

To expedite the project, the state government has now offered to provide free land on the Daspalla-Bolangir stretch and agreed to bear 50 per cent of the project cost.

 