Illustrative image – not actual.Kishangarh Gulabpura Tollway (K G Tollway) has received appointed date as 21 February 2018, from the National Highways Authority of India (NHAI) for a road project in Rajasthan.
The project envisages six-laning of Kishangarh to Gulabpura Section of NH-79A and NH-79 in Rajasthan (length 90.000 km) on DBFOT (toll) mode under NHDP Phase-V Package-I.
The project has a concession period of 20 years, including construction period of 910 days. The company has offered premium of Rs 186.30 crore; the premium payment will commence three years from the appointed date.
The total cost of this project is Rs 1,526 crore, out of which equity contribution/ internal accrual by the company will be Rs 506 crore and the remaining is funded through project finance of Rs 1,020 crore from a consortium of lenders.