Kesar Enterprises plans Rs.197 crore capexIllustrative image – not actual.

Kesar Enterprises, a Kilachand Group company, is planning capacity expansion of its sugar plant, increase its storage capacity at the Kandla and Kakinada storage terminals and also plans to set up a power plant with a total investment of Rs.197 crore.

Funds will be raised through borrowings of Rs.131 crore and internal accruals of Rs.45.10 crore, among other sources.

Sugar & Cogeneration: The company plans to spend Rs.90.13 crore on expansion of sugar capacity. Of  this, Rs.25 crore will be spent to modernise the sugar plant and increase its capacity from 6,500 tccpd to 7,200 tccpd and another Rs.64.39 crore will be invested to raise capacity to 10,000 tccpd. The modernisation project is scheduled for completion by November 2006 and expansion by November 2007.

Kesar Enterprises plans to set up a 25 MW co-generation power plant with an investment of Rs.70.04 crore.  The project is scheduled for completion by March 2007.

Storage Capacity: The expansion of storage (and handling) capacity at Kandla and Kakinada will cost Rs.15 crore and Rs.22 crore, respectively and is likely to go on stream by January 2007.

The current capacity of its storage division at Kandla Port Trust is 90,000 klpd and will be increased by 36,850 klpd. Terminal-I has 29 tanks with a capacity of 55,300 klpd while Terminal-II has 15 tanks with a storage capacity of 34,700 klpd. The company is putting up a 36,250 klpd class-A tank for storage.

The Kakinada storage terminal includes Rs.17.79 crore ERW jetty pipeline and Rs.18.66 crore seamless jetty pipeline.

Addendum on 11 February 2006

On 10 February 2006, the company's board of directors approved the project.

Original news date: 23 January 2006