Keralam to source power from NTPC’s thermal projectIllustrative image – not actual.

Keralam is set to receive up to 300 MW of electricity from the Sinnar thermal power project of NTPC in Maharashtra.

Aiming to address a sharp rise in demand and bridge peak-hour shortages, Chief Minister V D Satheesan stated that the state has also requested NTPC to establish a dedicated power plant to secure long-term electricity requirements. During the talks, NTPC expressed willingness to sign a power purchase agreement (PPA) for supplying power. Additionally, discussions reviewed progress on battery energy storage projects, specifically the 40 MW/160 MWh BESS initiatives at Pothencode and Sreekandapuram managed by NTPC Green Energy, which remain on track for commissioning by March 2027.

These comprehensive measures are designed to enhance the state's dispatchable power availability, and modernise long-term energy management networks across Keralam