Illustrative image – not actual.Gail has proposed to conduct a fresh feasibility study on the proposed petrochemicals complex at Cheemeni in Kasargod district of Kerala.
The project forms an important aspect of the gas co-operation agreement concluded between Gail and Kerala state government in July 2004. The agreement envisages an aggregate investment of Rs.10,450 crore by Gail in the state.
Gail is now in the process of scouting for consultant for undertaking the feasibility study.
Project Backgrounder: Kerala State Industrial Development Corporation (KSIDC), which holds the letter of intent for the petrochemicals complex, had appointed Engineers' India to undertake the project feasibility. The study, completed in 2001, recommended the setting up of a naphtha cracker complex with facilities for ethylene, polypropylene, benzene and LDPE among other products. The project was then estimated to entail an investment of Rs.7,000 crore.