The Kerala government has planned to lay emphasis on setting up of power projects and revamping of the State Electricity Board, during the current fiscal year.

 

It has been proposed to add 211.2 MW of power generation capacity to the State grid by commissioning new projects. This includes 34.2 MW of capacity coming from three new hydel projects.

 

An estimated 305.15 MW of capacity is under construction through new hydel projects. Besides, power capacity worth 438 million kwh of generation is likely to be added through expansion of existing hydel units.

 

In the power distribution sector, the government proposes to install 1,525 km of 11 KV lines, 8,100 km of low tension (LT) lines and 1,835 transformers. The government has also planned to give 3.78 new electricity connections.