The Kenya Railways Corporation intends to revamp 363 km of old railway lines with an investment of USD 40 million.

The lines include the 217 km Nakuru-Kisumu meter-gauge railway (MGR), the 77.8 km Gilgil-Nyahururu MGR branch line, and the 69.05 Kisumu-Butere section. Approximately USD 26.41 million have already been aside for the Nakuru-Kisumu line, USD 4.73 million for the Kisumu- Butere, and USD 8.8 million for the Gilgil- Nyahururu branch line.

The three lines will act as main trans-shipment points between the standard gauge railway, and road for freight traffic destined for areas beyond the Naivasha inland container depot, before the implementation of the Nairobi-Malaba SGR project.

Kenya Railways will also construct a new station at Kisumu as part of the project. The station will have components such as a manager’s office, reception, a waiting lounge and lobby, and approximately 50,000 sq ft of commercial space.