Illustrative image – not actual.The USD 278 million wind power project whose contract was awarded to a consortium of two Chinese firms – NARI Group Corporation and Power China Guizhou Engineering Company -- will add an additional 300 MW to the national grid following the completion of a 400 kV transmission line.
The power plant will result to a reduction in power tariffs once full evacuation of power from the wind farm begins. The 428 km power transmission line was initially supposed to cost KES 15 billion but the government had to engage a new contractor after Spanish firm Isolux Corsan went bankrupt.
Following the line delay, the government had up to 1 September 2018 to complete the line or pay damages of USD 10 million a month to Lake Turkana Wind Company thereafter.