Illustrative image – not actual.KEC International has bagged two turnkey contracts for power transmission projects from the Ministry of Electricity and Water of Kuwait, and the Power Development Corporation (PDC), Jammu & Kashmir.
The Rs.30 crore Kuwait project, envisages a 98.5-km double circuit transmission line to be completed in four sets of 33 KV each on a turnkey basis.
The Rs.87 crore J&K project envisages laying of a 67-km 400 KV, DC transmission line between Baglihar and Kishanpur.
Both the projects are scheduled for completion in the third-quarter of 2004.