Illustrative image – not actual.The scope of work for both the packages, 1 and 3, will include design, supply, erection, testing and commissioning of 25kV, 50Hz, single phase traction over head equipment, switching stations, traction substations, SCADA, general electrical service work, along with civil engineering work i.e. service buildings, quarters, tower car sheds and other associated work.
Work on Package-1 will be undertaken between sections Hospet (including)-Kudatini (including) and Tornagallu (including)-Ranjitpura (including) and sidings comprising 67 RKM / 187 TKM of Hubli Division of South Western Railway. The work will entail an investment of Rs 94.58 crore.
Work on Package-2 will be undertaken between sections Kudatini (excluding)-Guntakal (excluding) section and sidings comprising 71 RKM / 178 TKM of Guntakal division of South Central Railway and Hubli division of South Western Railway. The work will cost around Rs 86.92 crore.