Illustrative image – not actual.An MoU was signed between Karnataka and the Central Government, on 22 May 2002, under which the Karnataka Power Transmission Corporation (KPTCL) would receive Rs.279.04 crore for 2001-02, as a long-term loan and grant under the Accelerated Power Development Reforms Programme (APDRP).
The assistance amount, however, would include the Rs.29
crore which has already been given to the state when the Centre had initiated
the APDRP in February 2000. At that time, KPTCL had signed an MoU, which set a series
of milestones for reforms for making it eligible for the assistance.
The funds so granted would be used to implement the
APDRP in the 3 circles of Mysore, Bijapur and Belgaum.
The APDRP envisages structured reforms to ensure that
the state utilities enforce strict monitoring of power distribution to reduce
transmission and distribution losses to a reasonable level and plug the leakage
in revenue. Accordingly, KPTCL proposes
to provide metres to un-metered category of installations to reduce commercial
losses and also reduce technical losses by providing distribution transformers,
additional 11 KV lines and capacitors on LT side of distribution transformers.