Karnataka state government has ratified the payment security mechanism (PSM) for the independent power projects (IPPs) in the state. This follows the Prime Minister's Office (PMO) fixing a 10-week deadline for clearing all pending power projects.
The IPPs benefiting from the move include Nagarjuna Power Corporation's 1015 MW project at Mangalore and Jindal Thermal Power Corporation's 500 MW expansion project at Toranagallu near Bellary. The PSM would also be available to the state-owned Karnataka Power Corporation's 1,400 MW gas based power project near Bangalore.
The three-tier PSM involves an escrow cover for 70 per cent of the debt component, a state government guarantee and an irrevocable letter of credit amounting to one month's capacity charge at 85 per cent plant load factor.