Illustrative image – not actual.Karnataka Power Corporation (KPCL) is likely to issue a request for proposal (RFP) to pre-qualified bidders for the EPC works for the proposed Bidadi combined cycle power project (BCCPP).
The LNG based 700 MW power project is planned at an estimated cost of Rs 4,200 crore at Bidadi. In 2010, KPCL had floated a request for qualification (RFQ) from the interested bidders for the EPC works and shortlisted over five companies. The project has been approved by the state government. However, KPCL is yet to get one final approval from the state government before it signs the gas transportation agreement with the GAIL.
In June 2010, the state government had signed an agreement with GAIL to lay the gas pipeline between Dabhol in Maharashtra and Bidadi near Bangalore to transport gas. Subsequently, GAIL India began laying the pipeline and the work is likely to be completed within the next one year.