Illustrative image – not actual.Karnataka Government has accorded its approval for JSW Steel's plans to increase capacity at its Vijayanagar plant from 10 to 16 million tpa.
At present, the company is in the process to add a three million tpa blast furnace to take the Vijayanagar capacity to 10 million tpa. At the moment, the company is focusing only on 10 million tpa expansion which is slated to be completed by March 2011.
The company has now received the water supply approval from the Almati dam and is likely to set up a pipeline from the dam to the plant soon.
JSW Steel aims to attain 32 million tpa capacity by 2020, of which 10 million tpa each is planned in Karnataka, West Bengal and Jharkhand. The balance two million tpa will come from its Salem unit which is currently producing one million tpa.