Ministry of Water Resources has said that three lift irrigation projects have been taken up in the Bhima by the Krishna Bhagya Jala Nigama (KBJNL) and the Karnataka Neeravari Nigam (KNNL).
The Sannati Lift Irrigation Project designed to provide irrigation facilities to 16,000 hectare has been executed by the KBJNL, the Bhima Lift Irrigation Project designed to provide irrigation facilities to nearly 24,300 hectare has been implemented by the KNNL.
The construction of the barrage work of the Sannati Lift Irrigation Project is nearing completion. The construction of canals and distributaries to provide irrigation facilities to 16,000 hectares of parched lands in drought prone Chitapur in Kalaburagi district and Gurmitkal and Yadgir taluks in Yadgir district is also in progress.
A total sum of Rs 276.62 crore has been spent on the irrigation projects till the end of October 2015.
Itaga Sangam Lift Irrigation Project, implemented by the KBJNL tapping the available water in the Bhima, has been completed in all respects and 1,200 hectare of land has been brought under the irrigation network. Similarly, the Bhima Lift Irrigation Project is also in the advanced stages of completion.