Illustrative image – not actual.The Karnataka High Court has given the state government another 2 months for clearing the 1,000 MW coal based power project promoted by the Nagarjuna Group.
The extension comes after the Karnataka state
government made a plea for extension after the expiry of the four-month
deadline given by the High Court, on the ground that the subject had been
placed before the state’s Chief Minister.
The project promoters had already submitted their
alternative payment mechanism, as directed by the High Court on the basis of
the recommendations of Crisil Advisory Services. Crisil had suggested 3 options,
viz. a letter of credit, reform-based payment security mechanism and creation
of cess for creating a sinking fund for meeting the default payment obligations
outside consolidated fund. These proposals were submitted in May, 2002.
The delay in the final approval of the project by the
government has again resulted in the project financial closure being pushed
back.