Illustrative image – not actual.The Karnataka Cabinet has cleared the Rs.5,985 crore Upper Bhadra lift irrigation project to ensure irrigation to 1.07 lakh ha of land in Chitradurga district and cater to the drinking water needs of Kolar and Tumkur districts.
The project involves a drinking water component to cater to the districts of Kolar, Tumkur and Chitradurga, involving a total cost of Rs.2,596 crore while the irrigation component will cost Rs.3,388 crore.
Building pumping stations across Tunga and Bhadra rivers and widening the Ajjampura tunnel besides laying canals in Chitradurga district as also distributary channels and feeder lines in Tumkur and Kolar districts will also be taken up. The project will also provide drinking water to drought-prone districts of Tumkur and Kolar.
The five year project will be executed in four phases from 2008-09. Tenders will be called for taking up works of canals, distributaries and feeder channels in 18 packages.