Kanpur Metro Report submitted to UP govtIllustrative image – not actual.

The Detailed Project Report (DPR) of the Kanpur metro project, work on which started in March 2015, has been prepared by Rail India Technical and Economic Service (RITES) and the Lucknow Metro Rail Corporation (LMRC). The report has been submitted to Uttar Pradesh government.

The DPR has envisaged two corridors for the project. The first corridor begins from IIT Kanpur spanning up to Naubasta Chauraha and covers 23.785 km with an elevated stretch of 15.164 km and an underground stretch of 8.621 km.

The second corridor of 8.6 km stretch from Agriculture University to Barra-8 covers an elevated section of 4.19 km and an underground section of 4.41 km.