The Uttar Pradesh Metro Rail Corporation (UPMRC) has completed construction of 750 mtrs. tunnel in three months, under the Kanpur Metro Project. The ‘Nana’ tunnel boring machine (TBM) used for this project has reached Naveen Market Metro Station from Chunniganj by fixing 523 rings in the up-line tunnel.
The tunnelling will be carried out through the Naveen Market Underground Metro Station from one end to another and launch towards the Bada Chauraha Metro Station.
Similarly, in the underground stretch of Chunniganj to Naveen Market, Tatya TBM is constructing the down-line tunnel and has installed 323 rings out of 520.
In Corridor-I of the project, apart from the Chunniganj-Nayaganj underground section, another underground stretch from Kanpur Central to Transport Nagar Metro station, and an elevated section from Bara Devi to Naubasta are being constructed.