Kannur Airport to be ready by May 2016Illustrative image – not actual.

Kannur International Airport is expected to commence full operation from May 2016. The Rs 1,896 crore airport is being set up on EPC basis.

 

 

As of July 2015, about 57 per cent of the runway work and about 36 per cent of the passenger terminal building have been completed. Of the total 2061 acres of land required 1,277.93 acres have been acquired.

 